NEW QUESTION 29
During the troubleshooting phase, what is the first step?

  • A. Isolate
  • B. Repair
  • C. Verify
  • D. Test

Answer: C

 

NEW QUESTION 30
What is the maximum allowable horizontal cable length?

  • A. 30 m (100')
  • B. 90 m (295')
  • C. 10 m (33 ')
  • D. 50 m (164')

Answer: B

 

NEW QUESTION 31
Which of the following is permissible if the available firestop assembly is NOT capable of properly restoring the necessary fire rating?

  • A. Add more of the product to increase the rating
  • B. Move the installation to another location
  • C. Obtain written assistance from the manufacturer
  • D. Substitute products from another assembly

Answer: C

 

NEW QUESTION 32
Which of the following types of construction protects the optical fiber by supporting each strand of glass with a buffer coating extruded over the base optical fiber's 250 um acrylate coating?

  • A. Tight buffered
  • B. Loose tube
  • C. Ribbon
  • D. Single stranded

Answer: A

 

NEW QUESTION 33
What is the characteristic impedance of Series-6 coaxial cable?

  • A. 75 ohms
  • B. 100 ohms
  • C. 50 ohms
  • D. 25 ohms

Answer: A

 

NEW QUESTION 34
What is the minimum number of consolidation points that should serve an open office furniture cluster?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: A

 

NEW QUESTION 35
How much cable slack should be left in the work area after termination?

  • A. 3m (10')
  • B. 1m (3.3')
  • C. 1.2 m (4')
  • D. 0.5m (1.6')

Answer: B

 

NEW QUESTION 36
Which type of tester includes a set of modular plugs?

  • A. Cable-end locator kit
  • B. Multimeter
  • C. Inductive amplifier
  • D. Tone generator

Answer: A

 

NEW QUESTION 37
What is the most appropriate administration class for an infrastructure with multiple telecommunications spaces within one building?

  • A. Class 4
  • B. Class 2
  • C. Class 1
  • D. Class 3

Answer: B

 

NEW QUESTION 38
Which of the following is a floor serving space that serves as a point of termination for horizontal and backbone cables?

  • A. TE
  • B. EF
  • C. ER
  • D. TR

Answer: D

 

NEW QUESTION 39
A third 90-degree bend may be permitted in a conduit run if one of the bends is located within ____ of the cable feed end?

  • A. 450 mm (18")
  • B. 300 mm (12")
  • C. 483mm (19")
  • D. 375 mm (15")

Answer: B

 

NEW QUESTION 40
Which of the following topologies is the recommended topology for distribution systems in campus environments?

  • A. Tree
  • B. Ring
  • C. Hierarchical Star
  • D. Star

Answer: C

 

NEW QUESTION 41
What grade of plywood is recommended for use with ICT systems?

  • A. A/D
  • B. B/C
  • C. C/D
  • D. A/C

Answer: D

 

NEW QUESTION 42
Which of the following is a benefit of air-blown optical fiber cable?

  • A. It requires less testing than other types of cables
  • B. It is significantly cheaper than other types of cables
  • C. It can be recovered and reused

Answer: C

 

NEW QUESTION 43
What is the size of a rack-mounted unit (RMU)?

  • A. 45 mm (1.75")
  • B. 25 mm (1")
  • C. 38 mm (1.5")
  • D. 50 mm (2")

Answer: A

 

NEW QUESTION 44
The information transmitted by an ICT system can originate in two fundamental forms:

  • A. Light and sound
  • B. Analog and digital
  • C. Synchronous and asynchronous
  • D. Progressive and regressive

Answer: B

 

NEW QUESTION 45
You are terminating a category 3 cable. What is the maximum permissible amount of untwisting?

  • A. 25 mm (1")
  • B. 100 mm (4")
  • C. 75 mm (3")
  • D. 38 mm (1.5")

Answer: C

 